  • City of Saint John Eastern Wastewater Treatment Plant, Saint John, New Brunswick
  • Cahill, as a subcontractor to Pomerleau Inc, is providing all electrical and instrumentation installation services for a new 35,000 cubic metre per day sewage treatment plant owned by the City of Saint John
  • The project is divided into the following key areas:  Main Process Building, Blower Building, Primary and Secondary Clarifiers, Aeration Tanks and Administration Building.

Client:  Pomerleau Inc. 
Duration:  July 2009 - June 2011
Person Hours: In progress (20,000+)

« Back to Water Treatment Projects List

Project Scope

Electrical & Instrumentation